请在 下方输入 要搜索的题目:

The BCWS is $10,000 and the BCWP was determined to have a $7,000 worth, and the ACWP is $5,000. what is the Schedule Variance percent?A、-48%B、40%C、60%D、29%

The BCWS is $10,000 and the BCWP was determined to have a $7,000 worth, and the ACWP is $5,000. what is the Schedule Variance percent?
A、-48%
B、40%
C、60%
D、29%

发布时间:2025-07-11 10:24:35
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:D.29%