During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog? (choose the best answer)Options:
A、 As soon as possible after it is identified.
B、 When the Scrum Master has time to enter it.
C、 During the Daily Scrum after the Developers approve it.
D、 When the Product Owner identifies new work.