3 The quality objectives are approved in the conceptual stage of the project by the: A、Project EngineerB、Project ManagerC、Functional ManagerD、Quality Assurance ManagerE、Project Owner
3 The quality objectives are approved in the conceptual stage of the project by the:
A、Project Engineer
B、Project Manager
C、Functional Manager
D、Quality Assurance Manager
E、Project Owner