After the normal function test of an individual circuit has been completed and the circuit switched off. 


A、a duplicate check must be carried out in accordance with AWN 3.
B、a second function test must be carried out to verify the first.
C、the fuse should be removed and the circuit again switched on to check the isolation of the circuit concerned. 

发布时间:2025-09-02 21:27:06
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:C