Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?


A、 Corrective action
B、 Risk audit
C、 Technical performance measurement
D、 Earned value management

发布时间:2025-07-27 23:10:14
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:A