If the terms of the performance security specify its expiry date, and the contractor has not become entitled to receive the performance certificate by the date 28 days prior to the expiry date, the contractor shall extend the validity of the performance security until the works have been completed and any defects have been remedied.


A、正确;

B、错误

发布时间:2025-06-30 01:44:13
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:正确