When a company purchases land with a building on it and immediately tears down the building so that the land can be used for the construction of a plant, the costs incurred to tear down the building should be A. Amortized over the estimated time period between the tearing down of the building and the completion of the plant. B. Added to the cost of the land. C. Expensed as incurred. D. Added to the cost of the plant.

When a company purchases land with a building on it and immediately tears down the building so that the land can be used for the construction of a plant, the costs incurred to tear down the building should be
A、 Amortized over the estimated time period between the tearing down of the building and the completion of the plant.
B、 Added to the cost of the land.
C、 Expensed as incurred.
D、 Added to the cost of the plant.

发布时间:2025-07-08 02:33:05
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:B