The project has been going well until you recently discover a member of your development team has wasted 6 days working to complete his favorite feature of the project , even though that feature only has to be 50% implemented for the business to release it after the first iteration. This discovery comes as a shock to the entire team. How could this situation have BEST been avoided on an Agile project?


A、 By managing and monitoring the team closer
B、 By helping the customer understand that the completed feature will save time in the long run
C、 By making sure everyone on the team understands the charter of the project
D、 By making the developer check in their code at the end of the night

发布时间:2025-08-13 12:48:46
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:C