单选] 一个项目团队正在与另一个国家的开发团队合作开发软件。在进度审查期间,项目经理发现由于对客户需求有不同的解释而导致返工,进而导致完工日期延迟。项目经理应该怎么做? A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs. What should the project manager do?


A、与主要干系人召开会议,以明确需求Set up a meeting with key stakeholders to clarify requirements
B、已上报至项目指导委员会,并要求提供额外的时间Escalate to the project steering committee and request additional time
C、前往开发团队办公室推动进度Travel to the development team's office to push the schedule
D、与开发团队一起创建原型,以合并需求Create prototypes with the development team to confirm requirements